Flordeliz Guest House Construction Photos

May 2011 - Page 3

Flordeliz Guest House Construction - Page 1

Flordeliz Guest House Construction - Page 2

Flordeliz Guest House Construction - Page 4

Flordeliz Guest House Construction - Page 5

Flordeliz Guest House Construction - Page 6

Flordeliz Guest House Construction - Page 7

Flordeliz Guest House Construction - Page 8

Flordeliz Guest House Construction - Page 9

Flordeliz Guest House Construction - Page 10

Flordeliz Guest House Construction - Page 11

Flordeliz Guest House Construction - Page 12

Flordeliz Guest House Construction - Page 13

Flordeliz Guest House Construction - Page 14

Flordeliz Guest House Construction - Page 15

Flordeliz Guest House Construction - Page 16

Flordeliz Guest House Construction - Page 17

Flordeliz Guest House Construction - Page 18

Flordeliz Guest House Construction - Page 19

Flordeliz Guest House Construction - Page 20

Started construction on the 20m x 10m Flordeliz Guest House in December 2010. The construction is going well until now with completion scheduled in 1-2 months. This is the 3rd page starting in April of 2011. Click on the link above to see the earlier pictures.

PhilFlagMediumEmbossed.gif

Week of April 30, 2011

The floors and walls are done inside the rooms, and all of the soffets and attic vents are done. All 4 sides of the house have had the finishing cement appied. All of the dark tiles are on the front of the house. Next week, we will be adding the tiles on the vertical columns and starting to put tiles on the small porches.

IMG_0680.JPG IMG_0681.JPG IMG_0682.JPG IMG_0683.JPG IMG_0684.JPG

IMG_0685.JPG IMG_0686.JPGg IMG_0687.JPG IMG_0688.JPG IMG_0690.JPG

IMG_0693.JPG IMG_0704.JPG IMG_0706.JPG IMG_0707.JPG IMG_0708.JPG

IMG_0709.JPG IMG_0711.JPG IMG_0715.JPG

Week of May 7, 2011

Tiles are done on the front of the house except for columns. Columns will be done tomorrow. Terrace floors are done except for grout, next will be tiles for the bottom path area near the terraces. we order the windows in the next 2 weeks. The CRs have toilets installed and floor drains. Water will not be installed until electric work done.

IMG_1639.JPG IMG_1640.JPG IMG_1642.JPG IMG_1643.JPG IMG_1644.JPG

IMG_1645.JPG IMG_1646.JPG IMG_1647.JPG IMG_1648.JPG IMG_1649.JPG

IMG_1651.JPG IMG_1652.JPG IMG_1653.JPG IMG_1654.JPG IMG_1655.JPG

IMG_1661.JPG IMG_1662.JPG IMG_1664.JPG IMG_1666.JPG

Week of May 14, 2011

Got all the tiles in place in the front and sides of the house. Painting of the horizontal sections of the balustrade is being done now too. Work will start on the kitchen in the back soon. Tiles for the back should be available soon as well.

IMG_2406.jpg IMG_2407.jpg IMG_2408.jpg IMG_2409.jpg IMG_2410.jpg

IMG_2411.jpg IMG_2412.jpg IMG_2413.jpg IMG_2414.jpg IMG_2415.jpg

IMG_2416.jpg IMG_2417.jpg IMG_2418.jpg IMG_2419.jpg IMG_2422.jpg

IMG_2423.jpg IMG_2424.jpg IMG_2426.jpg IMG_2427.jpg IMG_2428.jpg

IMG_2429.jpg IMG_2430.jpg IMG_2431.jpg